Please read the attachments as we will be starting phase 4 in White Meadow Lake within the next week. Listed below are the order that the streets will be completed: 1. Valley View Dr and North Lake Shore Dr will be started within the next few days 2.Comanche Ave 3.Cherokee Ave 4.Erie Ave 5.Anderson Ave 6.Beach St 7.Iowa Ave Please follow the detour signs and plan some extra travel time if we are working on or around your street.
Update from NJNG January 9, 2017
Main Update:
We will be completing the main installation on Erie Ave in approximately 1 week. We will then install the gas main on the following streets:
Anderson Ave.
Beach St.
Iowa Ave.
We should be done with all the main installation in phase 4 of White Meadow Lake within the next 4 weeks.
Service Lateral Update:
We are currently installing service laterals in phase 4. We are installing the laterals in the following street order:
N lake Shore
Comanche
Valley View
Cherokee
Erie
Anderson
Beach
Iowa